Shenzhen Distribution Room Transformer Expansion and Reconstruction
Back to Projects
Industrial

Shenzhen Distribution Room Transformer Expansion and Reconstruction

Confidential

Project Location
Shenzhen, Guangdong, China
Completion Date
February 2025
Project Scale
1600A system
Project Duration
N/A

This project involved expanding the capacity of a distribution room transformer in Shenzhen, Guangdong, from 315KVA to 800KVA. The original rigid bus duct connecting the transformer to the low-voltage cabinet was removed due to incompatibility with the new equipment layout and the extremely constrained construction space. With a compressed project timeline, the owner selected Yanghua's 1600A universal-type flexible busbar. Unlike the original bus duct, the flexible busbar required minimal effort for installation — a single continuous run replaced the entire rigid connection. The product's lighter weight, smaller dimensions, and superior flexibility enabled rapid on-site routing and connection, dramatically shortening the construction period and reducing total project cost compared to custom-fabricated rigid bus duct alternatives.

Project Background & Challenges

The 315KVA to 800KVA transformer capacity expansion required replacement of the existing bus duct in an extremely confined construction space. The tight project schedule demanded a solution that could be installed quickly without pre-fabrication lead time, while maintaining full 1600A current-carrying capacity.

  • Extremely confined distribution room space leaving minimal clearance for equipment installation and conductor routing
  • Standard rigid bus duct requiring precise pre-fabrication measurements and extended manufacturing lead time
  • Compressed project schedule demanding same-day transformer replacement and power restoration
  • Need to maintain full 1600A current capacity within a dramatically smaller conductor cross-section

Solution

Yanghua supplied a 1600A universal-type flexible busbar that replaced the original rigid bus duct with a single continuous run. The product's lightweight, compact design and inherent flexibility enabled fast on-site routing and connection without requiring advance measurements or custom fabrication.

  • Deployed 1600A universal-type flexible busbar as a direct replacement for the removed rigid bus duct
  • Single continuous run eliminated all intermediate joints and the need for pre-fabricated custom sections
  • Lightweight and compact design enabled easy manual handling and rapid routing in confined spaces
  • On-site cut-to-length capability eliminated measurement-dependent lead times and accelerated installation

Project Results

315KVA to 800KVA
Transformer Capacity Upgrade
Same-day completion
Installation Time
Approximately 60% vs. rigid bus duct
Construction Period Reduction
100%
Pre-Fabrication Lead Time Eliminated