Kunshan Industrial Computer Room Power Renovation Project
Back to Projects
Data Center

Kunshan Industrial Computer Room Power Renovation Project

Confidential

Project Location
Kunshan, Jiangsu, China
Completion Date
July 2025
Project Scale
2000A system
Project Duration
N/A

This renovation project is located in an aging power distribution system within an industrial factory's computer room in Kunshan, Jiangsu Province. The renovation demanded high current carrying capacity within severely constrained installation spaces featuring numerous directional turns. The original multi-splicing rigid busbar plan required a large number of joints and was both bulky and difficult to install. Yanghua's solution utilized 630A and 1000A universal flexible busbars in a double-assembly configuration to achieve the required 2000A capacity. The compact form factor eliminated the need for extensive multi-conductor assembly, while the high flexibility allowed easy bending through all turns within the specified bending radius. This approach delivered significant savings in installation time, labor, and space while maintaining full electrical performance.

Project Background & Challenges

The aging industrial computer room required a 2000A-capable renovation within extremely tight spaces with many turns, where the original multi-splicing rigid busbar plan was too bulky, required excessive joints, and proved excessively difficult to install in the constrained environment.

  • Extremely limited installation space in the aging computer room restricting conventional busbar deployment
  • Complex routing with numerous directional turns requiring flexible conductor solutions
  • 2000A capacity requirement that the original rigid busbar plan could only meet through excessive multi-splicing
  • Retrofit environment demanding a non-disruptive, rapid installation approach to minimize downtime

Solution

Yanghua supplied 630A and 1000A universal flexible busbars configured in double-assembly to achieve 2000A capacity. The compact flexible conductors eliminated bulky multi-splicing, easily bent through all directional changes within the bending radius, and dramatically simplified installation in the tight computer room space.

  • Deployed 630A and 1000A universal flexible busbars in double-assembly configuration achieving 2000A capacity
  • Compact conductor dimensions replaced bulky multi-splicing rigid busbar trunking
  • High flexibility enabled easy bending through all turns within the rated bending radius
  • Simplified installation eliminated complex jointing, saving time and labor in the constrained retrofit space

Project Results

100%
Multi-Splice Joint Elimination
55%
Installation Time Reduction
40%
Space Savings in Equipment Room
45%
Installation Labor Cost Reduction